Development Update: Alba, Mason Point Release 5
Alba is the fifth release at Mason Point, a development whose name has become synonymous with affordable luxury living.
These elegantly crafted two and three bedroom townhomes and apartments showcase a balance of design which makes the most of the beautiful natural surroundings.
Construction is progressing well as follows:
- The first month of autumn brought long periods of settled weather and with that has come consistent progress on site.
- Works to the apartments have progressed much faster than forecast last month as the site team managed to get the Level Two floor installed two weeks ahead of schedule.
- Civil works have recommenced now that all in-ground service runs have been completed and as such it is expected that the roads will be fully sealed within three weeks.
- Works to townhomes G47 – 56 are progressing well with kitchens and bathrooms now fully installed and floor finishes due to go down within the fortnight.
- Townhomes in block G28 – G37 are now weather-tight with all windows now installed. Wall linings are due to commence next week with cladding works to take place concurrently.
- All structural works are now complete to Townhomes G38 – 46 with service rough-in’s well underway. Cladding works have also commenced and the roof is expected to be complete prior to the end of April.
Anticipated completion dates are as follows:*
- Townhomes 47-56 – July 2017
- Townhomes 28-46 – October 2017
- Townhomes 22-27 – November 2017
- Apartments – November 2017
Please find the latest construction photos below.
Have a question about your property purchase?
Contact the Customer Service team weekdays between 9am to 8pm on 1800 652 224 or email contact@parktrent.com.au.
*Completion date is an estimate only and may be subject to change due to circumstances beyond ParkTrent and the developers control.