Development Update: Alba, Mason Point Release 5
Alba is the fifth release at Mason Point, a development whose name has become synonymous with affordable luxury living.
These elegantly crafted two and three bedroom townhomes and apartments showcase a balance of design which makes the most of the beautiful natural surroundings.
Construction is progressing well as follows:
- Apartments are progressing well with concrete structure works now 90% complete. Framing to Level One is due to commence by mid-February. Perimeter blockwork and internal structural walls have now been installed also – beginning to see the tenancies and the car park coming out of the ground.
- The Townhomes are proceeding at an accelerated rate, roofing works are completed for Townhomes 47-56 and cladding works have commenced to the east elevation. A good bulk of the windows are expected to be installed by the end of February – the large expanses of glass will really enhance the natural landscape.
- Level 1 structure works are now complete for Townhomes 28-37 with timber frames being erected to Level 1 in early February. The balance of Townhomes have had all in-ground services works completed with a ground slab to be poured by mid-February.
Anticipated completion dates are as follows:*
- Townhomes 47-56 – July 2017
- Townhomes 28-46 – October 2017
- Townhomes 22-27 – November 2017
- Apartments – November 2017
Please find the latest construction photos below.
Have a question about your property purchase?
Contact the Customer Service team weekdays between 9am to 8pm on 1800 652 224 or email contact@parktrent.com.au.
*Completion date is an estimate only and may be subject to change due to circumstances beyond ParkTrent and the developers control.